Xray Inspection Process
The aPriori starting point Digital Factories define a single machine for this process.

Cost is based on the following formula:
Process Time = Visual Inspection Time Standard * Part Surface Area
Process time depends on the following:
Visual inspection time standard is inspection time per unit area (specified by the cost model variable visualInspectTimeStandard—5 min/m2 in aPriori starting point Digital Factories)
Part surface area (obtained from geometry extraction)