Piece Cost

Piece Cost = Material Cost + Labor Cost +
Direct Overhead Cost + Logistics Cost +
Setup Cost + Other Direct Costs

Piece cost is defined in the Site cost model global taxonomy module. Piece cost is the sum of the following per part costs:

  • Material cost (result of aggregating material costs from the current node’s children)

  • Labor cost (result of aggregating labor costs from the current node’s children)

  • Direct overhead cost: see  Overhead Costs per Part

  • Logistics cost (result of aggregating logistics costs from the current node’s children)

  • Setup cost: also known as “amortized batch setup”, this is the result of aggregating setup costs from the current node’s children.

  • Other direct costs (see Other Direct Costs)