Primary Direct Costs

Material cost and direct overhead cost are calculated using the formulas below.

Material Cost = (Part Volume *
Material Cost Per Volume / Utilization) / Final Yield

aPriori calculates the cost for material based on the following factors:

Material Cost Per Volume =
Material Cost Per Mass * Material Density

Material cost per volume is the product of the following quantities:

  • Material cost per mass (specified in the Material Selection dialog)

  • Material density (listed in the Material Selection dialog)

Labor Cost = Labor Rate * Labor Time / Final Yield

Labor cost is the product of the following:

  • Labor rate: this is the product of the following:

    • Machine property Labor Rate
    • Cost model variable laborRateAdjustmentFactor (1 in starting point Digital Factories)
    • Machine property Work Center Labor Rate Factor (1 in starting point Digital Factories)
  • Labor time (see Times below)

  • Final yield (see Yields)